County Planning

Application Details

Application no.: 08/91952 (map)
Site Reference: NF255
Location: Land at Plumley Wood and Farm, Burnt Hill, Nea Farm, Blue Haze and Blashford Quarries, Near Ringwood
Proposal: New Development comprising the proposed extraction of sand & gravel & deep sand (incorporating the diversion of public footpaths) with restoration to agriculture, commercial forestry, deciduous woodland & heathland & associated development including: 1. the construction of a mineral washing plant at Burnt Hill together with the storage of Plumley Wood mineral at Burnt Hill with restoration of the site to heathland; 2. extension of existing field conveyor system from Nea Farm Quarry to Plumley Wood (via Burnt Hill) including bridge sections over Harbridge Drove & public footpath at Plumley Wood; 3. the phased redevelopment of Blashford Plant site including the extension of the plant site & recycling operations into Lodge Field; 4. variation of conditions of Planning Permission No. 06/88238 including key variations to condition 2 (extension of time), 6 (hours of working), 24 (stockpile heights), 27 (screen bunding at Blashford) & 48 (storage capacity of recycled aggregates/arisings)
Received: 15/02/2008
Validated: 15/02/2008
Start of Public Consultation: 15/02/2008
Public Consultation Expiry: 16/04/2008
Decision: Granted
Decision date: 10/06/2009
Appeal Status: Appeal not lodged
Case Officer: Julia Davey
Case Officer Telephone: 01962 846732
Contact e-mail: planning@hants.gov.uk
Agent’s Name: Andrew Cadell
Agent’s Address: Tarmac Limited
Stancombe Lane
Flax Bourton
Bristol
Applicant’s Name: Tarmac Limited
Applicant’s Address: Tarmac Limited
Millfields Road
Ettingshall
Wolverhampton
Attachments:  

Application Form

Notice Under Article 6

Certificate Under Article 7

Supporting Statement

Supporting Statement Appendices

Design and Access Statement

Phased Working and Restoration Proposal

Environmental Health Comments

Non-Technical Summary

Environmental Statement (Report)

TS1 (Technical Study) - Planning Policy Assessment

TS2 - Air Quality Assessment

TS3 - Ecology

TS4 - Noise Report

TS5 - Highways Report

TS6a - Landscape Assessment (text only)

TS6b - Landscape Assessment (plans)

TS7 - Hydrology and Hydrogeology

TS8 - Agriculture Report

TS9 - Archaeology Assessment

Site Location Plan

Planning Application Boundary

Borehole Locations, Summary Geology and Cross Sections Plan

Geological Cross Sections A to C Plan

Geological Cross Sections D and E Plan

Block Phasing Plan (Sep 08)

Enabling Works A Plan (Sep 08)

Enabling Works B Plan (Sep 08)

Enabling Works C Plan (Sep 08)

Phase 1 Plan (Sep 08)

Phase 2 Plan (Sep 08)

Phase 3 Plan (Sep 08)

Phase 4 Plan (Sep 08)

Phase 5 Plan (Sep 08)

Phase 6 Plan (Sep 08)

Phase 7 Plan (Sep 08)

Phase 8 Plan (Sep 08)

Initial Restoration Plan (Sep 08)

Final Restoration Plan (Sep 08)

Burnt Hill:Landscaping Cross Section Plan (May 08)

Nea Farm: Conveyor and Landscaping Plan

Blashford Plant Site Redevelopment: Layout and Landscaping Plan (Phase 2) (Sep 08)

Blashford Plant Site Redevelopment: Landscaping Cross Sections Plan (Phase 2) (Sep 08)

Overall Site Plan for New Engineering Proposals

Burnt Hill Washing Plant (BHWP) Site Plan

BH Overland Conveyors Sections and Elevations Plan (Sep 08)

Nea Farm New Overland Conveyors Layout and Elevations Plan

Blashford Plant Site Redevelopment (BPSR) Layout Plan - Phase 1

BPSR Layout Plan - Phase 1 (Sep 08)

BPSR Layout Plan - Phase 2 (Sep 08)

BPSR Elevations Plan - Phase 2 (Sep 08)

Plumley Wood Restoration Plan (Sep 08)

Plumley Wood Restoration Cross Sections Plan (Sep 08)

Plumley Wood Enlarged Cross Sections through Receptor Properties Plan (Sep 08)

Burnt Hill Restoration Plan

Burnt Hill Restoration Cross Sections Plan

Blashford Plant Site Revised Restoration Plan

Blashford Plant Site Revised Restoration Cross Sections Plan

Further Info - Access to Plumley Wood

Additional - Covering Letter

Additional - Potential Washing Plant Locations Report

Additional - Noise and Vibration Assessment

Additional - Noise Measurement Tables

Additional - Washing Plant Layout Plan

Additional - Washing Plant Elevations Plan

Additional - Layout Overview and Landscaping Proposal Plan

Additional - Plant Layout: Phase 2 Plan

Additional - Plant Layout: Phase 3 Plan

Additional - Landscaping Cross Sections Plan

Additional - Noise Level Graphics

Clarification - Viewpoint A Normal Lens Image

Clarification - Viewpoint A Landscape Image Current

Clarification - Viewpoint A Landscape Image Phase 1

Clarification - Viewpoint A Landscape Image Phase 3

Clarification - Viewpoint A Landscape Image Phase 3 with Trees

Clarification - Viewpoint A Zoom Lense Image

Clarification - Viewpoint A Zoom Landscape Image Current

Clarification - Viewpoint A Zoom Landscape Image Phase 1

Clarification - Viewpoint A Zoom Landscape Image Phase 3

Clarification - Viewpoint A Zoom Landscape Image Phase 3 with Trees

Clarification - Viewpoint B Normal Lens Image

Clarification - Viewpoint B Landscape Image Current

Clarification - Viewpoint B Landscape Image Phase 1

Clarification - Viewpoint B Landscape Image Phase 3

Clarification - Viewpoint B Landscape Image Phase 3 with Trees

Clarification - Viewpoint B Zoom Lense Image

Clarification - Viewpoint B Zoom Landscape Image Current

Clarification - Viewpoint B Zoom Landscape Image Phase 1

Clarification - Viewpoint B Zoom Landscape Image Phase 3

Clarification - Viewpoint B Zoom Landscape Image Phase 3 with Trees

Clarification - Further acoustic information

Additional - Water Vole and Otter Survey

Additional - Great Crested Newt Survey

Additional - Aquatic Invertebrates Survey

(Sep 08) Amended and Additional Proposals Covering Letter

(Sep 08) Ecology - Amended and Additional Proposals

(Sep 08) Supporting Statement - Amendments

(Sep 08) Noise and Dust - Amended and Additional Proposals

(Sep 08) Phased Working and Restoration Proposals

(Sep 08) List of Plans with May 08 and Sep 08 Amendments

(Sep 08) Landscape and Visual Additional Info

(Oct 08) Palaeolithic Archaeology: Written Scheme of Investigations

(Oct 08) Additional Information - Covering Letter

(Oct 08) Additional Information - Noise

(Oct 08) Additional Information - Dust

(Oct 08) Additional Information - Lighting Installations

(Oct 08) Additional Information - Lighting Strategy

(Nov 08) Additional Information - Agricultural Land and Restoration Issues

Committee Report

Documents at Committee - Ringwood Forest Development Brief

Documents at Committee - Environmental HealthCcomments

Documents at Committee - Conditions

Plans at Committee - Overall Location Plan

Plans at Committee - Location Plan 1

Plans at Committee - Location Plan 2

Plans at Committee - Location Plan 3

Officers Report Article 30 Condition 18 (Lighting) 58 (Abstraction Point Detail)

Decision Notice Article 30 Condition 18 (Lighting) 58 (Abstraction Point Detail)

Condition 8

Condition 58