Application no.: 12/00912/HCC (map)
Site Reference: RM035
Location: Former Lafarge Site, Hollybush Lane, Nr Aldershot Hampshire GU12 5QA
Proposal: Development of the site to provide an end of life vehicle treatment facility and metal recycling facility, comprising of new buildings, hardstanding, weighbridges, perimeter screening and fencing, an extension to the road and associated road improvements, a footpath and a new car park for staff and public use, (part retrospective), development also including landscaping, the provision of a sustainable drainage system and the demolition of a concrete batching tower
Received: 19/10/2012
Validated: 19/11/2012
Start of Public Consultation: 19/11/2012
Public Consultation Expiry: 07/02/2014
Decision: Refused
Decision date: 15/01/2014
Appeal Status: Appeal not lodged
Case Officer: Julia Davey
Case Officer Telephone: 01962 846732
Contact e-mail: planning@hants.gov.uk
Agent’s Name: Integrated Skills
Agent’s Address: Integrated Skills Limited
Bell House
32 Bell Street
Romsey
Hampshire
Applicant’s Name: Mr George Boulden
Applicant’s Address: Hollybush Lane
Aldershot
Hampshire
Attachments:  

Site Notice

Notice of Decision

Application Form

Planning Statement

Design & Access Statement

(Add) Applicants Letter (2 Sept 2013)

(Add) Applicants letter (4 Oct 2013)

(Add) Applicants email (6 Dec 2013)

(Add) Applicants email (12 Dec 2013)

(Add) Construction Management Plan

(Add) Foul Water Treatment (23 Oct 2013)

(Add) Process Document (23 Oct 2013)

(Add) Proposed Tree Planing (2 Sept 2013)

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Response from David Mason re Transport Assessment

(Add) Letter Re Flood Risk Assessment (Feb 2013)

(Add) Aboricultural Report (March 2013)

(Add) Supplementary Noise Assessment (March 2013)

(Add) Proposed Tree Planting (21 Nov 2013)

(Add) Planting Plan (21 Nov 2013)

Site Location Plan

Application Boundary Plan

Proposed Site Layout Plan (March 2013

Elevation Plan for Main Building Plan

Elevations Plan for Building for Non Ferrous Metal

Plant and Machinery

(Add) Illuminance Plot Plan (4 Oct 2013)

(Add) Sections through Proposed Flooding Catchment Area Plan ( 23 Oct 2013)

(Add) Proposed Re-grading Levels to Suit Attenuation Storage Requirements (23 Oct 2013)

(Add) Proposed Site Sections (22 Nov 2013)

Non Technical Summary

Environmental Statement (ES)

ES Appendix A Extended Phase 1 Habitat Assessment

ES Appendix B Transport Assessment

ES Appendix C Landscape and Visual Impact Assessment

ES Appendix C Landscape and Visual Impact Assessment

ES Appendix C Landscape and Visual Impact Assessment (2 Sept 2013)

ES Appendix D Assessment of Noise Levels

ES Appendix E Flood Risk

ES Appendix E Flood Risk Appendix A

ES Appendix E Flood Risk Appendix B

ES Appendix E Flood Risk Appendix C

ES Appendix E Flood Risk Appendix D

ES Appendix E Flood Risk Appendix E

ES Appendix E Flood Risk Appendix F

ES Appendix E Flood Risk Appendix G

ES Appendix E Flood Risk Appendix H

ES Appendix E Flood Risk Appendix J

ES Appendix E Flood Risk Appendix K

ES Appendix E Flood Risk Appendix L

ES Appendix E Flood Risk Appendix M

ES Appendix E Flood Risk Appendix N

 