Highway Maintenance

2006/07 Schemes

Works are expected to begin on 1st April 2006.

Location

Duration

Start

Finish

ALTON

   

Southview Rise, Cherry Way

16 days

10 May 06

26 May 06

ANDOVER

   

Junction Road, Bishops Way

30 days

19 Jul 06

18 Aug 06

Millway Road

23 days

31 Jul 06

23 Aug 06

Upper Drove, Harrow Way

24 days

7 Aug 06

1 Sep 06

Walworth Road

29 days

22 Aug 06

20 Sep 06

The Drove, Eardley Avenue

22 days

31 Aug 06

22 Sep 06

Gallaghers Mead, The Crescent

21 days

13 Sep 06

4 Oct 06

Smannell Road

29 days

20 Sep -06

19 Oct 06

Charlton Road

52 days

2 Oct 06

23 Nov 06

Floral Way

29 days

30 Oct 06

28 Nov 06

London Road

34 days

9 Nov 06

13 Dec 06

BARTON STACEY

   

Roberts Road, Roman Way, East Road, West Road

32 days

20 Nov 06

22 Dec 06

BASINGSTOKE

   

Jasmine Road

3 days

4 Dec 06

7 Dec 06

Railway Footpath

15 days

4 Dec 06

19 Dec 06

Ringway West Footpath

10 days

11 Dec 06

21 Dec 06

Kempshott Lane

55 days

13 Dec 06

6 Feb 06

EASTLEIGH

   

Greenfinch Close, Maple Square, Greenwood Close

8 days

1 May 06

9 May 06

Coulsdon Road

10 days

5 May 06

15 May 06

FAREHAM

   

Burnt House Lane South, Pinewood Close

8 days

1 May 06

9 May 06

Grove Avenue, Merton Crescent, Central Road,


Haven Crescent, King George Road, Jubilee Car Park

25 days

5 May 06

30 May 06

Shenley Close, Blackbrook Park Avenue, East Lodge

16 days

24 May 06

9 Jun 06

Carlton Road

8 days

1 Jun 06

9 Jun 06

Norwich Close, Vine Close, Arundel Drive, Beaufort Avenue

32 days

5 Jun 06

7 Jul 06

Bishopsfield Road, Longmynd Drive

27 days

20 Jun 06

17 Jul 06

West Street Roundabout, New Town

17 days

10 Jul 06

27 Jul 06

Fareham Park Road

14 days

21 Jul 06

4 Aug 06

Abbeyfield Drive

11 days

31 Jul 06

11 Aug 06

FLEET

   

Elms Road, Cypress Drive

11 days

29 May 06

9 Jun 06

Avondale Road, Pinewood Hill, Chestnut Grove,
Brookly Gardens

38 days

6 Jun 06

14 Jul 06

Branksomewood Road

10 days

26 Jun 06

6 Jul 06

Connaught Road, Burnside

27 days

4 Jul 06

31 Jul 06

GOSPORT

   

Wilmott Lane, Anglesea Road, Station Road, Hill Park Road

23 days

14 Aug 06

6 Sep 06

Parham Road

10 days

1 Sep 06

11 Sep 06

Albermarie Avenue on hold

 

5 Jun 06

5 Jun 06

Grove Road on hold

5 Jun 06

5 Jun 06

HAVANT

   

Cumberland Avenue (including Birch Tree Drive)

17 days

12-Sep-06

29-Sep 06

Andrew Crescent, Winsor Road, Lucerne Avenue,
Bernina Avenue

21 days

22 Sep 06

13 Oct 06

Park Avenue

7 days

9 Oct 06

16-Oct-06

Bound Lane, Salterns Lane, West Haye Road,
Wheatlands Avenue

46 days

12 Oct 06

27 Nov-06

Lovedean Lane

27 days

31 Oct 06

27 Nov 06

Sunnymead Drive, Esher Grove, Haslar Crescent,
Charlesworth Drive)

40 days

22 Nov 06

1 Jan 07

Sinah Lane Hayling Island

21 days

15 Dec 06

5 Jan 07

Horndean Road

18 days

4 Jan 07

22 Jan 07

The Dale, The Rise

23 days

16 Jan 07

8 Feb 07

RINGWOOD

   

A31 Footpath & Footbridge

7 days

6 Sep 06

13 Sep 06

WHITEHILL

   

Horseshoe Crescent

10 days

22 May 06

1 Jun 06