Roads and Transport

Lindford - B3002 Lindford Road and B3004 Liphook Road

This webpage provides an outline of the planned works associated with the  traffic management works for the Lindford Road/Liphook Road in Lindford.

The works are due to start on Monday 19 September and are expected to be completed in February 2012.  The programme includes a two week break over Christmas and the New Year.

Hampshire County Council have awarded a contract to Mildren Construction Ltd for the construction of the traffic management features. The works will generally take place between 9am and 4.30pm when temporary traffic signals will be used as necessary.  In order to construct the features safely it will be necessary to implement some temporary road closures, which are described below.

Road closures and Diversions

The works at the Fiveways junction will require temporary road closures to enable the works to be undertaken safely.  These will involve the temporary closure of Chase Road and Frensham Lane at their junctions with Liphook Road, for up to 35 days, commencing on 3 October.

These will be followed by a two day weekend closure of Lindford Road, Liphook Road, Headley Road, Chase Road and Frensham Lane at the Fiveways junction, which is planned for the weekend of 5/6 November 2011.

In the event that these dates have to change then an update will appear here.

The road closures and temporary traffic diversions will be signed, and access to all businesses and properties will be maintained.  The attached plan shows the planned diversion routes.

Lindford Road Closures Map Download Acrobat Reader to view this PDF 355kb

More details about the proposals

The traffic management proposals aim to slow traffic along the Lindford Road and Liphook Road as it passes through Lindford village.  The proposed calming measures of raised tables and build - outs include five informal, uncontrolled crossings to assist local access to the Elmfield Court shopping area for pedestrians.

The scheme features;

  • new signage at Lindford Bridge
  • a central traffic island north of the Fiveways junction
  • a raised speed table (flat top road hump) over the Fiveways junction
  • a raised speed table and road crossing by Elmfield Court
  • new lay-bys either side of Cricket Lea
  • a raised speed table and road crossing by the link to Lindford Wey
  • a traffic pinch point and road crossing either side of Mount Pleasant Road
  • a traffic pinch point and road crossing by Orchard Drive

Detailed drawings of the proposals can be viewed below;

Location 1 Download Acrobat Reader to view this PDF 778kb        Location 2 Download Acrobat Reader to view this PDF 721kb        Location 3 Download Acrobat Reader to view this PDF 888kb

Location 4 Download Acrobat Reader to view this PDF 632kb        Location 5 Download Acrobat Reader to view this PDF 483kb        Location 6 Download Acrobat Reader to view this PDF 470kb

Picture
(Click on image to enlarge)

Lndford Traffic Management Scheme Thumbnail Image 212kb

Further details about the scheme including the report leading to the decision to implement the scheme can be found using the link below by entering the Item Reference number 2513 and clicking Search

http://www3.hants.gov.uk/councilmeetings/advsearchmeetings/meetingsitemsummary.htm

Contact details

If you have any queries about the scheme please either phone our contact centre on 0845 603 5638, or email roads@hants.gov.uk.