Roads and Transport

A30 Hartford Bridge Flats and Blackbushe junction improvement: public consultation

22 January 2015

Summary of work completed

Work has continued on the existing east and west islands in the central reserve on the approaches to the staggered junction A30/A327/Blackbushes Rd, and to the A30 roundabout at the entrance to British Car Auctions (BCA).

Road construction has started in these areas with the first two of three layers of asphalt being laid, together with the drainage.

The replacement kerbs on all four corners of the roundabout at BCA have been laid and construction of the new improved footway access to the bus stops has been formalised. Road construction has been completed to most areas, including the roundabout.

January to February 2015

Most of the work to date at the A30/A327/Blackbushes Rd junction has been undertaken to prepare of a temporary roundabout to improve the traffic management and facilitate a larger working area on the south side of the site.

This temporary arrangement will improve traffic flow at the junction and help to create a safer working environment for the contractor and the public. During the next phase we will begin construction of the new permanent roundabout including drainage on the south side of the site.

Download plans

Overview

Approximate construction timescales for the various components of the scheme are:

  • Start on site from 10 November 2014
  • Blackbushe Roundabout from November 2014 until January/February 2015
  • Construction of the new roundabout at the junction of A30 and A327 from February/March until May 2015.

Please note that due to restrictions on the use of the government grant that is paying for the scheme, the fourth arm of the new roundabout (that will connect with Blackbushes Road) will be delivered at a later date. This work is being delivered in a separate package and was not able to be delivered alongside this project. This was highlighted during the consultation held in summer 2014.

Main features of the scheme:

  • introduction of a three arm roundabout at the priority junction of the A30 with the A327
  • realignment of the existing roundabout junction at Blackbushe Airport
  • banning of a right turn into and out of Blackbushes Road from the A30

More information

Register for updates by email

Contact Us

Telephone:

  • 0845 603 5638
  • 01329 225 398 calls from within the UK
  • 0845 603 5625: Minicom for hearing and speech impaired customers within Hampshire

By post:

Strategic Transport
Economy, Transport and Environment Department
Hampshire County Council
SO23 8UD

Financial contribution from the Department for Transport

The Hartford Bridge Flats and Blackbushe scheme is valued at £2.5 million with a contribution of £1.47 million from the Department for Transport through the pinch point programme.

DFT logo