Proposal: The construction and operation of a 8 MWE Pyrolysis Advanced Conversion Technology (ACT) plant including a 2 MWE Anaerobic Digestion Plant associated office, visitor centre, with new access road and weighbridge facilities, solar panels, associated landscaping and surface water attenuation features
Received: 07/09/2012
Validated: 13/09/2012
Start of Public Consultation: 13/09/2012
Public Consultation Expiry: 18/07/2014
Decision: Refused
Decision date: 20/06/2014
Appeal Status: Appeal not lodged
Case Officer: Kristina King
Case Officer Telephone: 01962 846496
Contact e-mail: planning@hants.gov.uk
Agent’s Name: SLR Consulting Ltd
Agent’s Address: SLR CONSULTING LTD
TREENWOOD HOUSE
ROWDEN LANE
BRADFORD ON AVON
WILTSHIRE
Applicant’s Name: Clean Power Properties Ltd and Network Rail Infrastructure Ltd
Attachments:  

Public Notice

Public Notice - Amendments

Public Notice - Decision

Application Form

(Add) Applicants Letter re The Proposed Off Set Land (11 June 2014)

(Add) The Proposed Off Set Land (11 June 2014)

Additional Information (Nov 2012)

Additional Information Letter (Dec 2012)

Volumn 1 Planning Statement

Design & Access Statement

Additional Infomration Applicants Letter (9 Dec 2013)

(Add) Illustrative Master Plan (9 Dec 2013)

(Add) Site Access Options (9 Dec 2013)

(Add) Addendum to Planning Application (9 Dec 2013)

(Add) Addendum to Chapter 10 of the Environmental Statement Fuel Tank Insepction (9 Dec 20

(Add) Addendum to Chapter 7 Environmental Statement -Air Quality & Odour (9 Dec 2013)

(Add) Ecology 12 (9 Dec 2013)

(Add) Addendum to Chapter 8 the the Environmental Statement - Noise (9 Dec 2013)

Non Technical Summary

Statement of Community Involvement

BREEAM Pre Assessment

Location Plan (Sept 2012)

Existing Stie Sections

Proposed Site Layout

Proposed Floor Plan

Proposed Floor Plan Level 01

Proposed Plan Roof Level

Proposed Floor Plan Level 00 & Level 01 Office, Eduction & Reception Area

Proposed Sections

Proposed Site Sections

Proposed Elevations 1

Proposed Elevations 2 Anaerobic Digestion (AD) Tanks

Site Access Options (Sept 2012)

Habitat Mitigation Plan

Volumn 2A Chapter 1- Intoduction

Chapter 2 -Site Description

Chapter 3 - Descrpition of Development

Chapter 4 - Planning Policy

Chapter 5 - Alternatives

Chapter 6 - Traffic

Chapter 7 - Air Quality

Chapter 8 - Noise

Chapter 9 - Hydrology

Chapter 10 - Land Quality

Chapter 11 - Landsape

Chapter 12 - Ecology

Chapter 13 - Cultural Heritage

Chapter 14 - Socio Economic

Chapter 15 - Cumulative Impact

Chapter 16 -Summary and Conclusions

Volumn 2B - Appendix 1- Scoping Request

Appendix 2 - Scoping Opinion

Appendix 3 - Summary of Scoping Issues

Appendix 4- - Arbricultural Survey, Categorisation and Implictions Assessment

Appendix 4- Tree Survey Schedule

Appendix 4- Tree Constrains Plan 1

Appendix 4- Tree Constraints Plan 2

Appendix 6 - Traffic Assessments -Traffic Survey Part 1

Appendix 6 - Traffic Survey Part 2

Appendix 6 - Traffic Survey Part 3

Appendix 6 - Traffic Survey Part 4

Appendix 6 - Traffic Survey Part 5

Appendix 6 - Traffic Survey Part 6

Appendix 6 - Traffic Survey Part 7

Appendix 6 - Existing Traffic Flows

Appendix 6 - Baseline Traffic Flows

Appendix 6 - Baseline Capacity

Appendix 6 - Development Flows

Appendix 6 -With Development Flows

Appendix 6 - With Development Site Access

Appendix 6 - With Development A303

Appendix 6 - Site Access Options

Appendix 7 - Air Quality - Technical Appendix Atmospheric Dispersion Modelling

Appendix 7 - Discrete receptor locations modelled

Appendix 7 - Discrete ecological receptor locations modelled

Appendix 7 - Predicted 24-hr SO2 impacts

Appendix 7 - Predicted 15-minute SO2 impacts

Appendix 7 - Predicted annual PM10 impacts

Appendix 7 - Predicted annual NO2 impacts

Appendix 7 - Predicted annual SO2 impacts

Appendix 7 - Predicted annual HCI impacts

Appendix 7 - Predicted annual TOC impacts

Appendix 7 - Predicted annual Cadmium impacts

Appendix 7 - Predicted annual Mercury impacts

Appendix 7 - Predicted annual Arsenic impacts

Appendix 7 - Predicted annual Chromium (VI) impacts

Appendix 7 - Predicted annual Nickel impacts.pdf

Appendix 8 - Noise Glossary of Terminology

Appendix 9 - Flood Risk Assessment

Appendix 10 - Preliminary Contamination Risk Assessment Report

Appendix 11 - Landscape Designations Plan

Appendix 11 - Landscape Character Plan (National)

Appendix 11 - Landscape Character Plan (Local Character Areas)

Appendix 11 - Topography

Appendix 11 - ZTV for Building Mass Only

Appendix 11 - ZTV for 20M High Stack

Appendix 11 -Photo viewpoints

Appendix 11 - Landscape Strategy Plan

Appendix 12 - Ecology Appendicies- Phase 1 Habitat Plan

Appendix 12 - HBIC Protected & Notable Species Records

Appendix 12 - Botanical Survey & Assessment

Appendix 12 - Bat Survey & Assessment

Appendix 12 - Reptile Survey & Assessment

Appendix 12 - Bird Survey & Assessment

Appendix 12 - An Invertebrate Survey

Appendix 13 - Cultural Heritage Appendicies

Appendix 13 - Designated Heritage Assets

Appendix 13 - HER Information

Appendix 13 - HER Information