Application No.
|
Site Reference
|
Location
|
Proposal
|
|
BDB/68775
|
BAG009
|
Willis Museum, Market Place, Basingstoke RG21 7QD (Planning Application)
|
Removal of C20th false ceilings from front ground level gallery, restoration work and conversion to temporary exhibition area with new entrance lobby, secondary security glazing and internal glazed screen. Relocation of reception and cafe to rear gallery. Refurbishment of rear first floor gallery. New external ramp and secondary level entrance on west side. New and railings and replacement handrails. Remodelled first floor WCs including accessible WCs outside listed demise (Planning Application)
|
|
BDB/68613
|
BA057
|
Humbly Grove Oilfield, Weston Common, The Avenue, Lasham, Alton
|
Variation of condition 5 of planning permission BDB/46946 F26326/9/CMA 00/00024/CMA to allow the export of oil from the site by tanker for a temporary period
|
|
BDB/68298
|
BA057
|
Humbly Grove Oilfield, Weston Common, The Avenue, Lasham, Alton
|
Erection of a single storey control post building adjacent to the main compound
|
|
BDB/68299
|
BA126
|
Land adjoining M3 Motorway at Andwell Lane, Andwell, Basingstoke
|
Construction of a noise bund
|
|
BDB/67781
|
BAE016
|
Dove House School, Sutton Road, Basingstoke, Hants
|
Provision of two double temporary classroom unit, for a temporary period
|
|
BDB/67780
|
BAE016
|
Dove House School, Sutton Road, Basingstoke, Hampshire
|
Conversion of existing atrium space to a teaching space with the introduction of a new metal roof and roof light supported off existing steel frame and new floor
|
|
BDB/67677
|
BAE035
|
Chineham Park Primary School, Shakespeare Road, Popley, Basingstoke RG24 9BP
|
New single storey Childrens Centre with associated external works
|
|
BDB/67668
|
BAE050
|
Chiltern Primary School, Chiltern Way, Basingstoke, Hants RG22 5BB
|
New single storey Childrens Centre with associated external works
|
|
BDB/67621
|
BA057
|
Weston Common Wellsite, The Avenue, Lasham
|
Importation of compressed natural gas by trailer and discharge to generate electricity involving the setting out of a trailer discharge area
|
|
BDB/67497
|
BAE012
|
Kings Furlong Junior School, Upper Chesnut Drive, Basingstoke
|
Renewal of field gate with side panels, renewal of pedestrain gate
|
|
BDB/67425
|
BAE015
|
Cliddesden Primary School Cliddesden Basingstoke RG25 2QU
|
Small resource room, single storey and matches detailing, materials and style of existing building
|
|
BDB/67298
|
BAE056
|
Testbourne Community School, Micheldever Road, Whitchurch, Hampshire RG28 7JF
|
Change of use application - existing site managers house to be used as a special needs teaching space
|
|
BDB/67254
|
BAE046
|
Manor Field Infants School, Haydn, Road, Brighton Hill, Basingstoke RG22 4DH
|
New extension comprising of a multi-purpose room and entrance area together with alterations within the existing infant school to provide toilets & office accommodation
|
|
SSC/2007/0190
|
BA057
|
Humbly Grove Oilfield, Weston Common, The Avenue, Lasham
|
Request for Screening and Scoping Opinion for proposed export of gas by trailer from Singleton to Humbly Grove Oilfields, installation of a comproessed natural gas unit at Singleton and importation of gas to generate electricity
|
|
BDB/66661
|
BAE055
|
Marnel Infant & Junior School, Shetland Road, Popley Way, Basingstoke RG24 9PT
|
Expansion of Marnel Infant & Junior School - 55sqm entrance extension, 50sqm courtyard extension Junior School - 770sqm extension containing 6 classrooms & new main hall.
|
|
BDB/66344
|
BAE016
|
Dove House Special School, Sutton Road, Basingstoke RG21 5SU
|
Provision of one modular temporary classroom unit, for a temporary period, to provide extra teaching space, including WC's within the unit - paths and access routes included in this application
|
|
BDB/66252
|
BAE023
|
The Clere School & Technology College, Burghclere, Newbury
|
Proposed new single storey science laboratory in an existing school courtyard
|
|
BDB/66136
|
BAE002
|
Brighton Hill Community School, Brighton Way, Basingstoke RG22 4HS
|
Provision of one double and one single modular temporary classroom unit for a temporary period
|
|
BDB/66045
|
BAE024
|
Burnham Copse Primary School, New Church Road, Tadley, Basingstoke RG26 4HN
|
The extension and refurbishment of the existing former junior school building into a 1 Form Entry Primary School.
|
|
BDB/66030
|
BA125
|
Basingstoke Sewage Treatment Works (STW) Basingstoke
|
New inlet works building and new blower house
|